Voting details

Request to approve Contract Change Order No. 1 to the agreement with David Crye General Engineering Contractor, Inc., in the amount of $298,428; and authorize the Director of Public Works, or designee, to execute and process the change order; and increase the total construction contingency amount to $396,428 for the Arroyo Grande Creek Waterway Management Program Phase I Project. District 4.

Recommendation:
The Board approves as recommended by the County Administrative Officer.
For: 5
  • Adam Hill
  • Bruce S. Gibson
  • Debbie Arnold
  • Lynn Compton
  • John Peschong
Against: 0
Abstained: 0
Recused: 0
Absent: 0